Grafstal
Switzerland - Ground-source heat pump
| Summary The purpose of the project was to build a low energy and low cost prefabricated house without compromising the comfort. The house is a 3-storey building with the third floor being a loft in regular use. Due to the overall reduced energy consumption in low energy houses the proportion of the heat required for DHW increases from 30% to 40%. |
|
|
| This sets new requirements for a heating system. In this residence a vertical ground-source heat pump provides heating from October to April and DHW all year round. The COP of the 4.9 kW heat pump is 4.6 at test conditions.
|
||
Building and design values
| Building type: | Single-family house | |||
| Location: | Grafstal, Switzerland | |||
| Year of construction: | 1998 | |||
| Number of storeys: | 3 | |||
| Heated floor area (m2): | 174 | |||
| % of total floor area (%): | No data (cellar unheated at 13ºC) | |||
| Design outdoor temperature (ºC) | Heating: | -11 | Cooling: | - |
| Design indoor temperature (ºC) | Heating: | 20 | Cooling: | - |
| Degree days | Heating: | 3 308 | Cooling: | - |
| Base temperature for degree days (ºC) | Heating: | 12 | Cooling: | - |
Heating and cooling
| Application: | Space heating and DHW | |||
| Heat pump type(s): | Brine-to-water (same heat pump for heating and DHW; but different operation regimes) | |||
| Heat pump installed capacity (kW) | Heating: | 4.9 B0W351 |
Cooling: | - |
| Refrigerant: | R290 | |||
| Heat source | Brine | |||
| Details: | Circulation pump 69 W (ground source), Pump 49 W (heat distribution) | |||
| a) Type of ground heat exchanger: | Vertical, 32 mm diameter double U-pipe | |||
| b) Borehole depth (m): | 100 | |||
| c) Pipe length (m): | 4 x 100 | |||
| d) Heat transfer fluid: | Ethylene glycol (25%) | |||
| e) Flow rate (l/h): | 1 600 | |||
| Distribution system(s): | Floor heating elements/water without thermostatic valves | |||
| Supply and return temperature (ºC) | Heating: | 34/292 | Cooling: | - |
| Auxiliary system: | None | |||
| Heat pump design: | Heating demand of the house (20ºC, air change rate=0.3/h) according to a SIA3 model was calculated as 215 MJ/m2a. The actual amount used was 208 MJ/m2year (22ºC indoor). The return temperature control is dependent on outdoor temperature. Under normal conditions, the pump is turned on/off up to 6 times. The minimum operation time is 1.5 hours. Up to three times per year (on the coldest days), the heat pump is on without interruption. DHW (38 l/person/day, 50ºC) is provided all year round. |
|||
| Supplementary system: | Single room air heat recovery unit. | |||
| Heat pump system completion date: | 1998 | |||
Performance (NTH4)
| Energy for heating, DHW and ventilation1 | Heat pump | Aux. heating system | Auxiliaries2 |
| Energy input (kWh/year): | 2 649 | - | 522 |
| Energy output (kWh/year): | 12 625 | - | 2663 |
| Energy cost (CHF/year)4: | 498.81 | - | - |
| Cost tariff (CHF/kWh)5: | 0.16/0.10 | - | - |
| Coefficient of performance (COP) | |
| Heating: | 4.6 (space heating) |
| Test conditions: | B0/W35 |
| Cooling: | - |
| Test conditions: | - |
| Heat pump cost breakdown | |
| Heat pump including control unit (CHF): | 9 700 |
| Installation, including transport (CHF): | 3 400 |
| Ground Source incl. Installation (CHF) | 11 000 |
| Capital cost (excl. heat pump, ground source and installation) (CHF): | 19 350 |
| Maintenance (CHF/year): | 150 |
Comparison of annual costs
Options 1-6:
Oil-fired boiler (16 kW), electric backup for DHW; balanced ventilation with heat recovery
Air-to-water heat pump (4.6 kWth) and exhaust-air heat pump water heater
Gas-fired boiler (13 kW), electric backup for DHW; balanced ventilation with heat recovery
Wood-fired burner, electric boiler for DHW, balanced ventilation with heat recovery
Integrated heat pump system for space heating, DHW, ventilation and heat recovery, back-up electric boiler (for application in "passive house").
Ground-source heat pump (4.9 kWth), electric backup for DHW, balanced ventilation with heat recovery
Operational experience and other comments (NTH4)
This project has demonstrated that a low energy and low cost prefabricated house can be built without compromising the comfort. Similar 3-storey houses exist on this housing estate in an area about 556 m above the sea level. The average annual temperature is 9.5ºC.
Some heat pump-related improvement ideas were raised after completing the monitoring programme:
The circulation pump for the ground source could be replaced by a type using only one third of the electricity (70W).
The heat pump capacity should be lower than required rather than higher than required.
Low temperature distribution systems (Tsup>25°C) are self-regulating. Mixing or thermostatic valves are not necessary.
Overheating in fall and spring may be a problem. Shading devices are essential.
The equipment should be in a heated space (to avoid heat losses from storage vessel).
Ordering information
Technical Handbook in German:
(NTH4): Th.Afjei, A.Bühring, M.Dürig, A.Huber, P.Keller, E.Shafai, P.Widmer, G.Zweifel: Kostengünstige Wärmepumpenheizung für Niedrigenergiehäuser: Technisches Handbuch - Grundlagen, Planungsvorgehen und Praxisbeispiele, Schlussbericht Phase 4, Bundesamt für Energie 2000
to be ordered for CHF 40.- at:
| Last updated: 1 March 2004 |
| The world's leading information centre on heat pumps |