Lowell

Massachusetts, USA - Ground-source heat pump

 

Summary
Basic layout. Space conditioning control is critical for many quilt displays. A standing column geothermal heat pump was installed when this historic building, the New England Quilt Museum, was renovated and the former natural gas and electric systems replaced. The museum was designed for maximum heating andcooling loads of 211 kW (60 tons) . Prior to the retrofit the building was analysed for the geothermal heat pump feasibility and economic advantages. The wells are located under a nearby parking lot. The seasonal performance factor (SPF) of the heat pump is about 4.2.


Building and design values

 
Building type: Museum
Location: Lowell , Massachusetts, USA
Year of construction: 1919
Number of storeys: 3
Heated floor area (m2): No data
% of total floor area (%): No data
Design outdoor temperature (ºC) Heating: No data Cooling: No data
Design indoor temperature (ºC) Heating: No data Cooling: No data
Degree days Heating: 4 230 Cooling: No data
Base temperature for degree days (ºC) Heating: 18 Cooling: No data


Heating and cooling

 
Application: Space heating and cooling
Heat pump type(s): Water-to-water
Heat pump installed capacity (kW) Heating: 215 kW (6x35) Cooling: As heating
Refrigerant: R22
Heat source Groundwater
Details: See additional information
a) Type of ground heat exchanger: Standing column well (2)
b) Borehole depth (m): Column depth 457 (1500 ft)
c) Pipe length (m): No data
d) Heat transfer fluid: Water
e) Flow rate (l/h): No data
Distribution system(s): Fan coils
Supply and return temperature (ºC) Heating: 55/45 Cooling: -
Auxiliary system: No data
Heat pump design: No data
Supplementary system: The existing gas boiler has remained in place as a backup for the winter season. It has not been required since the retrofit.
Heat pump system completion date: Early 1995


Additional information
The heat pumps are on a simplified control scheme. The existing pneumatic control system was and remains non-functional. The building loop water temperature is manually set and automatically controlled by two aquastat controls. The aquastat controls are set with an approximate 2ºC (7 F) differential between 'call' temperatures. Each of the two banks of the three heat pumps is sequentially called by the temperature differentials. After the first heat pump, for example, 1 or 4 is called, the subsequent heat pumps within that 3-unit bank are called by set time delays. As the first bank is called, the first standing column well pump starts and water flows simultaneously through all three heat pumps in that bank. The concept schematic.

If the first bank cannot satisfy the building loop temperature and the building water loop falls more than 2ºC (7 F), the second bank is called. The second bank starts the second well pump, the large twoway motor valve opens and the water flows through all six heat pumps and the heat pump 4 starts, with 5 and 6 following within 3-8 minutes.
Experience has shown that the temperature in the museum does not drop over prolonged periods, such as long weekends, when the heating is not on. This is because of the large thermal mass of the building (thick granite walls).
The standing column wells serve three heat pumps each. The wells are provided with a bleed mechanism, which allows a rapid re-stabilisation (15-30 minutes) of the well in the event of excessive winter or summer load.


Performance

 
Energy Energy savings are over 60%.


Coefficient of performance (COP)
Heating: About 4.2
Test conditions: Seasonal performance


Heat pump cost breakdown
Heat pump only (USD): 215 000 total cost of heat pumps and wells
Installation (USD):
Capital cost (excluding heat pump) (USD):
Maintenance: No data


Alternative system (if has been considered) No data


Fuel cost No data


Payback No data


CO2 emissions No data


 
Operational experience and other comments
The manual on-off control of the heat pumps and the thermal inertia of the building have created long periods without heat pump operation. These allow the standing column wells to 'recover' more than typical installations. However, when the heat pumps are in operation these periods tend to be longer and the wells at higher temperatures.

 

Energy comparison.

Water-to-water heat pumps are preferential for retrofits.
Older buildings often have oversized air handlers and radiation. Water-to-water heat pumps can be operated at smaller evaporator-to-condenser temperature differences, increasing the efficiency.
Expensive or complex control systems are not required.
Small commercial retrofits with existing electric or fossil heating and chiller cooling can achieve attractive savings. The annual total building operational costs can reduce by 50-65% if geothermal heat pumps are used.


Contacts

 

Contact 1:

John Logan

    Company: Water Energy Distribution
    Role: System design
    Address: 15 Wawenock Road
Raymond, Maine 04071
USA
    Telephone: + 1 207 655 7529
    Fax: + 1 240 414 8924
    Email: geomaine @ maine.rr.com

 

 
Last updated: 1 March 2004
The world's leading information centre on heat pumps